|
Sardar
Sarovar Project
1. Catchment Area Treatment
For SSP in Phase-I (directly
draining sub-watersheds) a total of 143017 ha. area is
treated against a total targeted area of 179180 ha. up to
June, 2001.
2. Compensatory Afforestation
An area of 13386 ha. of
forest land was diverted by MOEF against the submergence.
Party States have prepared the plans for plantation of 42155
ha. and against this, the progress up to June, 2001 is 42064
ha. The Compensatory Afforestation works also required
4200 ha. of forest land which was diverted for R&R
work of PAFs . The progress achieved so far is 4198 ha. The
map depicts the compensatory afforestation works.
3. Command Area
The command area of the
Project is fixed, based on the areas included by NWDT for
irrigation in Gujarat. The gross command area is 3.43
million ha. The culturable command area is 2.12 ha. To
safeguard development of irrigation in the vast command,
mitigating measures have been determined requiring control
and monitoring in the following areas.
- Drainage water logging and
soil salinity
- Water quality
- Potential impacts on Flora
and Fauna
- Effects on public health
- Socio economic aspects
4. Flora, Fauna & Carrying
Capacity
A large number of studies
have been carried out for assessment of the environmental
impacts emanating from the submergence of the land by the
SSP by premier institutes, and, Action Plans have been
developed by the Govt. of Gujarat based on recommendations of these study groups. Similar plans by the
States of M.P. and Maharashtra are under formulation.
However, corrective steps in form of increased carrying
capacity of the degraded catchment through massive
afforestation are already on the verge of completion.
Gujarat have developed a sanctuary known as Shoolpaneshwar
sanctuary to accommodate the wildlife moving out from the
submergence area.
5. Seismicity
Steps have already been taken
in designing of the project as per the recommendations of
the dam safety panel and seismic designs have already been
implemented. For monitoring reservoir induced seismicity,
nine seismological monitoring stations have been established
around the periphery of the reservoir.
6. Health
Baseline data on health have
been generated through series of studies and epidemiological
studies and impact assessment studies have been carried out
by the State Health Departments, premier institutes like
Topiwala National College, Mumbai, Gandhi Medical College,
Bhopal in association with State Health Departments and
plans have been drawn up with Action Plans prepared. These
Action Plans are under implementation. A map showing the
proposed health facilities around the periphery of the
reservoir is given p below.
7. Archaeology
Detailed inventories and
surveys have been carried out by the Archaeological Survey
of India, Anthropological Survey of India, State Department
of Archaeology & Museum, M.P., Maharashtra and Gujarat
to ascertain the archaeological and anthropological remains
in the valley.
Plans have been drawn up for
the protection of identified monuments and these are under
implementation.
8. Fisheries
Studies have been conducted
by the premier institutes like Central Inland Capture
Fisheries Research Institute and the Universities engaged in
limnological research, Barkatulla University, Bhopal, Rani
Durgawati University, Jabalpur, Vikram University, Ujjain in
association with State Fisheries Developments to generate
baseline data for conservation of aquatic eco-system, plans
have already been drawn up for implementation.
Indira Sagar
Project
1. Catchment Area Treatment
(Directly Draining)
Status as on March, 2001
Total
Target 62975
Progress
51810
2. Compensatory Afforestation
Status as on September, 2000
Total
Target 80945
Progress
70031
3. Command Area Development
The Government of Madhya Pradesh has
submitted command area development plan. The project on
completion will provide annual irrigation to 1.69 lakh ha.
The implementation of the plan would be
taken up in three phases for completion by September-2007.
The study on impact of Agro chemicals, run-offs from fields on
surface & ground water quality in the command area has
been assigned to Jawahar Lal Nehru, Krishi Vishwavidhyalaya,
Jabalpur. An MOU for this work was finalised. An allocation
of Rs.24.5 lakh was made. Studies have commenced and are
making progress.
4. Flora, Fauna
and Carrying Capacity
Detailed studies were
entrusted to the Wildlife Institute of India, Dehradun in
December 1989 and were completed by March 1994. The final
study report is submitted.
Besides this, the Friends of
Nature's Society, Bhopal, has completed the preparation of
Wildlife Retrieval and Conservation Plan.
Actions have been taken by
NVDA to implement the recommendation of the WLI regarding
declaration of National Park & protected areas. Matter
is under consideration by the State Govt.
5. Fisheries
Development
The studies of certain
aspects of fisheries have been included in the Limnological
studies which is being conducted by three Universities of the
State. Studies in the Upper Narmada, (Bargi Reservoir) is
being conducted by
Rani Durgawati University, Jabalpur, studies in the Middle
Narmada (Tawa, Barna and Kolar Reservoirs) by Barkatullah
University, Bhopal, studies in the Lower Narmada by Vikram
University, Ujjain. All the three Universities have
completed the studies in their respective areas as per MOU
and final report is available. Accordingly Action Plan has
also been drawn up & is presently under scrutiny of NCA.
Aquatic fauna has also been
covered under the studies completed by Friends of Nature
Society, Bhopal. The draft report of FONS is also available.
Action plan submitted earlier is being updated.
6. Seimicity
and Rim Stability
The reservoir competency
survey has been done by GSI and report is submitted. In the
report, GSI suggested further studies for some patches of
narrow water divide. However environment sub-group decided
not to have further studies as experts were of the opinion
that there was no water loss between Mandla and Rajghat.
Establishment of 10 nos. of seismic
observatories in the Narmada Sagar Complex area is being taken up
by NVDA. Order has been placed and supply has commenced.
Procurement of Micro Earthquake recorders is already done. In
the mean time on the initiatives taken by NVDA, CWPRS has
already installed instruments to record, pre-impounding
data, for undertaking seismic studies at ISP at Omkareshwar
& Maheshwar projects through Analogue micro earthquake
recorder & strong motion oscillograph as an interim
measure. Data will be interpreted by IMD.
7. Health Aspect
A note on health aspects of
ISP prepared by NVDA was examined in the Ministry of E&F
and comments were sent for modifying the report. NVDA has
submitted the revised plan costing Rs.748.73 lacs for the
preventive and curative aspects of health. Regarding
preventive aspects, a MOU has been signed with the
Department of Preventive and Social Medicine, Gandhi Medical
College, Bhopal. Five half-yearly reports were received. For
studies on health aspect in project impact areas of SSP and
ISP, work is proposed through a cell of monitoring and
evaluation under the Directorate of Health Services, Bhopal.
The approved plan is being implemented.
8. Archaeological and
Anthropological Survey Archaeology
A survey of the 254 villages
is required for the identification of archaeological
monuments falling within the submergence area. The State
Department of Archaeology and Museum, Bhopal was entrusted
with the survey of these villages which has been completed.
The state Department have already submitted an action plan
for relocation of monuments of Archaeological significance.
This plan is being implemented.
Archaeological Survey of
India has also completed survey of 167 villages for
centrally protected monuments and for identification of
monuments which may be of significance. Implementation of the action plan
is already initiated.
Only lower bastion in north
of the Joga Fort is likely to be affected by scour action of
water and action is being taken by the concerned agencies to
ensure safety of monuments.
Excavation of the early
historic mound in village Khedinama in Hoshangabad district
is completed and report is available in NCA. Ancient tools
& artifacts have been found. Recently, State Department
has reviewed the action plan and has proposed shifting of 10
monuments and 5 excavation of sites in addition to the
earlier proposal of collection of sculptures &
excavation at Khedinama
9. Anthropology
Efforts are being made for
the retrieval of bio-cultural material from Narmada Basin. A
lot of information has been gathered from the field which
generated immense data of Socio-Anthropological
significance.
Rashtriya Manav
Sanghralaya has constituted a working group for the
retrieval of bio-cultural material in Narmada Basin. Survey
of tribal art and handicraft entrusted to M.P. Adivasi Kala
Parishad is completed and report is available. Besides
Anthropological Survey of India has covered these studies
under its own project called "People of India", A
Narmada Salvage plan was also launched by the Anthropological
Survey of India recently and the entire area was scanned and
some ancient tools have been found. |