The requirements cited in the letter of June 1987
I June, 1987 that catchment area treatment programme and
rehabilitation plans be drawn up and completed ahead of
reservoir filling would imply that the work was to be done
pari-passu. as far as catchment area treatment programme is
concerned, with the filling of reservoir. Even though the
filling of reservoir started in 1994, the impoundment
Award was much less than the catchment area treatment which
had been affected. The status of compliance with respect to
pari- passu conditions indicated that in the year 1999 the
reservoir level was 88.0 meter, the impoundment area was
6881 ha (19%) and the area where catchment treatment had
been carried out ;was .128230 hectares - being 71.56% of the
total work required to be done. The Minutes of the
Environmental Sub-group as on 28th September 1999 stated
that catchment area treatment works were nearing completion
in the states of Gujarat and Maharashtra. Though, there was
some slippage in Madhya Pradesh, however, overall works by
and large were on schedule. This clearly showed that the
monitoring of the catchment treatment plan was being done by
the Environmental Subgroup quite effectively.
Compensatory
Afforestation : The Judgement
While granting approval in 1987 to the
submergence of forest land and/or diversion thereof for
the SSP, the Ministry of Environment & Forests had
laid down a condition that for every hectare of
forestland, submerged or diverted for construction of the
project, there should compensatory, afforestation on one
hectare of non-forestland plus reforestation on two
hectare of degraded forest. According to the State of
Gujarat, it had fully complied with the condition by
raising afforestation in 4650 hectares of non-forest areas
and 9300 hectares in degraded forest areas before 1995-96
against the impoundment area of 19%. The pari-passu
achievement of afforestation in Gujarat was stated to be
99.62%.
If afforestation was taking place on waste
land or lesser quality land, it did not necessarily follow,
as was contended by the petitioners, that the forests would
be of lesser quality or quantity
Command area Development :
The Judgement
The SSP will provide irrigation water for
a cultivable command area of 1.9 million hectares in Gujarat
and 75,000 hectares in Rajasthan. The introduction of fresh
water to the drought-prone areas of Gujarat will create
obvious benefits for the farming communities. In order to
safeguard these benefits, control and monitoring was
suggested by the Secretary, Ministry of Environment &
Forests and Chairman of the Environment Sub-group in the
following areas from time to time :
- Drainage, water logging and soil
salinity;
- Water quality
- Forest loss
- Potential impact on flora and fauna
- Effects on public health
- Socio-economic impacts.
Pursuant to the above, fifty in-depth studies
had been carried out by the State Governments of Gujarat and
Rajasthan and some of the studies were still in progress.
One of the main objectives of carrying out these studies was
to prevent excessive use of ground water and water-logging.
There is no reason whatsoever as to why
independent experts should be required to examine the
quality, accuracy, recommendations and implementation of the
studies carried out. The Narmada Control Authority and the
Environmental Sub-group in particular have the advantage of
having with them studies which had been carried out and
there is no reasons to believe that they would not be able
to handle any problem, if and when, it arises or to doubt
the correctness of the studies made.
It is thought unlikely that any
significant negative environmental impacts will occur over
the next 30 years as a result of the project. Some possible
adverse effects have been identified - the main one being the
effect of flood attenuation on Hilsa migration. These needs
to be monitored and more studies undertaken to better
understand the conditions which trigger spawning. Beneficial
impacts in this period include reduced flooding and more
reliable dry season flows as well as an overall improvement
of the health and well being of the people to the reliable
domestic water supply, improved nutrition and enhanced
economic activity."
The above report clearly demonstrates that
the construction of dam would result into more regulated and
perennial flow into the river with an overall beneficial
impact. It is also evident that until all the dams are
constructed upstream and the entire flow of river is
harnessed, which is not likely in the foreseeable future,
there is no question of adverse impact including the fishing
activity and the petitioner's assertions in this regard are
ill-conceived.
Flora, Fauna : The
Judgement
That number of studies were carried out
and reports submitted. It was observe that the submergence
area and catchment area on the right bank of the proposed
reservoir exhibited a highly degraded ecosystem which was
in contract to the left bank area where there was fairly
good forest cover forming part of Shoolpaneshwar
Wildlife Sanctuary. With regard to the study of fauna, the
said report indicated that a well-balanced and viable
ecosystem existed in the Shoolpaneshwar Sanctuary.
Moreover, with the construction of dam, availability and
soil moisture will increase and support varieties of
plants and animals.
Health : The Judgement
That large number of studies had been
carried out on the health of villagers including studies
on water related diseases in SSP command area including
the area downstream of the dam. The study of M.S.
University in 1983 and other studies concluded that the
most common diseases in the basin were Malaria, Scabies,
Dysentery and Diarrhea. Of these only a threat to malaria
needed to be of concern. The study concluded that the
incidence of hygiene-related diseases other than Malaria
could be reduced by better water availability. The Gujarat
Work Plan covered villages within 10 KMs radius of the
reservoir including re-settled population and made
provisions for the monitoring, surveillance and control of
Malaria. The principle features of the Gujarat Work Plan
included establishment of a hospital at Kevadia near the
dam site, strengthening of laboratory facility including
establishment of mobile unit, residual insecticidal
spraying operations etc. This showed that the area of
public health was in no way being neglected.
Archaeology : The
Judgement
The area of submergence was stated to be
rich in archaeological remains but it still remained to be
studied. It was contended that there was danger of rich
historical legacy being lost and even a small increase in
the dam height would threaten to submerge many of the
sites listed in the report of the Archaeological Survey of
India. There were stated to be five monuments which would
be affected at the dam height of 90 meter or above and no
work was stated to have commenced to protect any of the
five monuments.
It is emphasized that no Centrally or state protected
cultural sites were located in the submergence area of the
project. In Gujarat, the Department of Archaeology concluded
that the temples of Shoolpaneshwar and Hampheshwar were
important monuments and should be moved to a higher level.
Sites were selected for constructing new Shoolpaneshwar and
Hampheshwar temples in consultation with temple trustees.
Shoolpaneshwar had been relocated and reconstructed near
Gora, about 15 Km downstream from the present location.
Hampheshwar was also constructed at higher ground in
consultation with the temple trustees and Pranpratistha was
also planned on 22nd to 24th April, 2000 i.e. before the
temple was submerged.