|
1980 |
Project
report of SSP prepared by GOG submitted to CWC for
clearance. |
|
|
Narmada
Water Scheme,1980 published in Gazette on 10-9-80 by
GOI NCA started functioning from Dec.1980. from New
Delhi. |
|
1985 |
Ministry
of Forest published guidelines for release of forest
area for other projects including rehabilitation for
river valley projects.
Narmada
Valley Development Authority (NVDA) set up for
construction of Narmada projects in MP. |
|
1986 |
Environment
(Protection) Act,1986 enacted by Parliament. |
|
1987 |
Work on
main dam of Sardar Sarovar Project started in April.
On
24.6.87 MOEF accorded environmental clearance to SSP
and ISP on certain conditions.
Composition
of NCA modified by GOI on 3.6.87, including union
secretaries of MOEF, MOW, MOP and chief secretaries of
party states and Secretary, MOWR as its Chairman. |
| |
MOEF
conveyed the approval for diversion of 13385.45 ha of
forest land in Gujarat, Maharashtra and M.P. for SSP. |
|
1988 |
Sardar
Sarovar Narmada Nigam (SSNL) was created as public
company in April 1988 by GOG. |
|
1990 |
Head
quarters of NCA shifted to Indore from New Delhi. |
|
1991 |
NCA
released submergence schedule, village-wise in each of
three states, corresponding to different heights of dam
during construction. |
|
1992 |
GOG
established Sardar Sarovar Punarvasavat Agency (SSPA) |
|
1994 |
Narmada
Bachao Andolan files a civil writ petition No. 319/94
in Supreme Court of India against SSP date on 15.4.94 |
|
1995 |
On
5.5.1995 the Hon’ble Supreme Court directed to
maintain the height of Dam Block No 30 to 46 (in the
spillway portion) at 80.3 m (excluding humps) |
|
1999 |
GOG
setup Grievance Redressal Authority (GRA) with justice
P.D.Desai as its Chairman on 18.2.99
The
Supreme Court gave permission for raising Dam blocks
30 to 46 up to 85m (excluding 3m high hump) vide its
dated 19.2.99
Grievance
Redressal Authority were appointed by M.P. and
Maharashtra Govts also under the Chairmanship of Mr.
Justice S.P.Kurdukar and Mr. Justice G.G.Sohani. |
|
2000 |
On
18-10-2000 the Supreme Court gave permission for
raising block 30 to 46 up to 90m.
As per
the directions of the Apex court the further raising
of dam beyond 90m will be only pari-passu with the
implementation of the relief & rehab. Measures and
on clearance by R&R subgroup of NCA in
consultation with GRA.
In Dec.
2000 GOG raised the spillway Blocks (30 to 46) of the
dam up to EL to 90m. |
| |
NCA
prepares action plan for completion of Sardar Sarovar
dam up to 110m by June 2003 and upto FRL by June 2005. |
|
May,
2001 |
Permission
was accorded for construction of 3 m high hump in
Block 31 to 45 of the spillway of SSD at EL + 90 m
keeping in view the safety of the down stream works of
dam. |
|
August, 2001 |
Construction of IBPT by
SSNNL, permitted by GOMP. |
|
May, 2002 |
NCA in its 64th Meeting
(Emergency) held on 17th May, 2002, permitted
SSNNL to raise the height of Sardar Sarovar Dam from
EL 90.0m to EL 95.0m for spillway block No.30 to
46 and SSNNL completed the construction by June 2002.
Construction of 3m stream lines hump on main spillway
blocks NO.31 to 45 leaving the end blocks 30 and 46
without hump was also permitted. |
|
May, 2003 |
NCA in its 66th Meeting
(Emergency) held on 14th May, 2003, permitted
SSNNL to raise the height of Sardar Sarovar Dam from
EL 95.0m to EL 100.0m for spillway block No.30
to 46 and SSNNL completed the construction by June
2002. Construction of 3m stream lines hump on
main spillway blocks NO.31 to 45 leaving the end
blocks 30 and 46 without hump was also permitted. |
|
March, 2004 |
NCA in its 70th Meeting
(Emergency) held on 12-13 March 2004, permitted
SSNNL to raise the height of Sardar Sarovar Dam from
100.0m to 110.64m for for spillway block No.30
to 46 as per the approved design. Other
spillway blocks are also to be raised to elevation as
adopted for hydromatic model studies to estimate
afflux / submergence area. |
|
March, 2006 |
NCA in its 76th Meeting
(Emergency) held on 08 March 2006, permitted SSNNL
to raise the height of Sardar Sarovar Dam to
121.92m as per approved design. The project
authorities should comply with the conditions laid
down by the sub groups of NCA and complete the above
construction by end of June, 2006. The project
authorities should ensure that the non overflow blocks
are raised to safe elevations or suitable measures are
taken. So as to avoid overtopping of these
blocks. Particular case is to be taken by all
the party states in preparing of contingency plans to
provide timely safeguards in case of any untoward
incident and insure that there is no submergence
before rehabilitation. |