5) Narmada Main Canal Sub-Committee:
|
||||||||||||||||||||||||||||||||||||||||
Functions:
1. To decide the phasing and to co-ordinate construction programmes of Sardar Sarovar Project Unit-II Canals with a view to obtaining expeditiously optimum benefits during and after the completion of the construction of the project having due regard to the availability of funds.
2. Obtaining from the concerned States periodical progress reports both as to works and expenditure, and on receipt of such reports review the progress of construction of different sub-units of the project (Unit-II) and whenever necessary advise the States concerned on the steps to be taken to expedite the works.
3. Scrutiny and approval of design of the Narmada Main Canal.
4. Resolving differences, if any, arising between Rajasthan and Gujarat on figures of cost in respect of Narmada Main Canal for the purpose of sharing of cost.